The purple pipe has a limit

Cover: The Purple Pipe Has a Limit  10,000 acre feet a year left on SAWS recycled water system for data centers, river flows and other uses

On November 3, the board of the San Antonio Water System (SAWS) got a briefing titled “High Volume Requests.” Its slides, in the board packet posted on October 28, set out what the utility means to do about data centers on its recycled water system: limits on “water intensive cooling technologies,” a “Fee by Agreement” bridge for the infrastructure new customers need, an expedited cost of service study in 2027 and a recycled water impact fee “during 2028 update.” Three days later the San Antonio Express-News reported the plan. A week before that, the City Council had voted 9 to 2 to require council approval, case by case, for every new data center, the San Antonio Report wrote.

The numbers behind it reached the board in March. A 15-slide briefing titled “Data Centers,” from Donovan Burton, the utility’s senior vice president for water resources, showed data centers using 211 acre-feet of drinking water in 2023, 176 in 2024 and 98 in 2025. Their recycled water use went the other way, from 196 to 243 to 297 acre-feet. By November, requests on file came to about 600 acre-feet of drinking water and “~3,000+” of recycled water, “some under negotiations.”

I believe the San Antonio case is worth reading for any utility with a data center in its pipeline, because SAWS already did what most people ask for. It moved the cooling demand off drinking water. The board packets show what happens next: the cheaper water has a limit too, and it was priced to attract customers.

SAN ANTONIO WATER SYSTEM · DATA CENTERS AND RECYCLED WATER29 Oct 2025Councilman asks staff for data center rulesCITY13 Jan 2026Mayor at the SAWS board: costs of large loads“particularly for large load customers like data centers”3 Mar 2026Board briefing: Data Centersuse by year, requests of ~3,000+ AF, six policy options7 Jul 2026Recycled water master plan contract$1.5M; a 30-year capital plan; 2 trustees voted noOct 2026AWWA report on evaluating data centerswith Carollo EngineersNATIONAL29 Oct 2026Council: case-by-case approval, 9 to 2staff had recommended by-right with standardsCITY3 Nov 2026Board briefing: High Volume Requestsfees, service rules, cooling limitsNextService rule change to the boardpotable and non-potable service splitNext“Fee by Agreement” bridge, then councilDuring 2027Cost of service study, expedited2028 updateRecycled water impact feeusing the master plan
From a council request to a fee proposal. The board saw the numbers in March and the proposals on November 3; a recycled water impact fee waits for the 2028 fee update.San Antonio Report, 29 Oct 2026; SAWS board packets of 3 Mar 2026 (draft minutes of 13 Jan; Data Centers briefing), 7 Jul 2026 (master plan award) and 3 Nov 2026 (High Volume Requests briefing, slides 15 and 16); AWWA report page, Oct 2026; Express-News, 6 Nov 2026.

Why the data centers moved to the purple pipe

SAWS has run a direct recycled water system since 1999. A July 2026 board slide describes “130 miles of purple pipe,” 114 customers, 122 million gallons a day of pumping capacity and 12.1 million gallons of storage. Recycled water “offsets nearly 10 percent of potable water demand,” staff told the board in September. The pipes are purple, which is how the system got its name.

The utility made that water cheap on purpose. The March briefing put the recycled rate at 39.6% of the residential potable rate, 46.8% of the general rate (multifamily, commercial and industrial) and 20.5% of the irrigation rate. In 2026 the standard recycled rate is $2.3772 per 1,000 gallons for the first 748,000 gallons a month, per the rate schedule in the October packet. Recycled customers also skip the water supply fee and the Edwards Aquifer Authority fee, according to SAWS’s recycled water user handbook (p. 37). The Express-News, reporting Burton’s explanation, called the discount “intentional, because SAWS wants large users to use the treated wastewater instead of using large amounts of drinking water for uses that don’t require it.”

Residential39.6%
General46.8%
Irrigation20.5%
Wholesale44.7%
All potable classes39.8%
SAWS’s recycled water rate as a percent of its potable rate, by customer class, in 2026. The discount is the reason large users take recycled water. The same briefing says recycled revenue covers 95% of the cost of service in 2026: $6.49 million of revenue against $6.79 million of cost.San Antonio Water System, Board of Trustees packet, 3 Mar 2026, Data Centers briefing, pp. 12 and 13. General includes multifamily, commercial and industrial.

For data centers it worked. The drinking water figure fell by more than half in two years while recycled use grew by half (derived from the briefing’s table). The November slide puts data centers at 0.1% of SAWS’s potable water use and 1.25% of its recycled water use today. With the pending requests, it projects 0.3% and 12%.

Drinking waterRecycled water
  • 2023: 407 (Drinking water 211 AF; Recycled water 196 AF)
  • 2024: 419 (Drinking water 176 AF; Recycled water 243 AF)
  • 2025: 395 (Drinking water 98 AF; Recycled water 297 AF)
Water used by data centers in San Antonio, in acre-feet a year, as SAWS reported it to its board in March. Drinking water use fell by more than half from 2023 to 2025 while recycled water use rose by about half (derived). Requests on file came to about 3,000 acre-feet more, with “several unknown”.San Antonio Water System, Board of Trustees packet, 3 Mar 2026, Data Centers briefing, p. 8 (Data Center Water Usage). One acre-foot is about 326,000 gallons.

How much recycled water there is to sell

The supply of recycled water is set by how much wastewater the city sends to the treatment plants. As the Express-News put it on November 6, SAWS “only has as much wastewater as its customers produce.” Staff told the board in September that recycled flows “have not significantly increased despite the city being 40 percent larger than 30 years ago.”

The March briefing shows where the 2025 output went. The water recycling centers produced 157,834 acre-feet. Fifty thousand was reserved for CPS Energy, the city-owned power utility, for its Calaveras and Braunig lakes, and another 50,000 “was allocated for downstream flows under SAWS’ bed and banks permit,” per the draft minutes. Recycled water demand was 19,322 acre-feet, which left 38,512 “available for other uses.”

Allocated to CPS EnergyAllocated to downstream flowsRecycled water demandAvailable for other uses
Acre-feet, 2025
50,000
50,000
19,322
38,512
Values
TierAcre-feet, 2025
Allocated to CPS Energy50,000
Allocated to downstream flows50,000
Recycled water demand19,322
Available for other uses38,512
Where the 157,834 acre-feet produced by SAWS’s water recycling centers in 2025 went, as the March board briefing laid it out. Two allocations of 50,000 each, to CPS Energy and to downstream flows, come before any recycled water customer. Customers used 19,322; 38,512 was left “available for other uses”, and the briefing adds that actual availability is site-specific.San Antonio Water System, Board of Trustees packet, 3 Mar 2026, Data Centers briefing, p. 9 (WRC Effluents in 2025).

The limit is in the pipe. Burton told the board on September 1 that the system “was planned for about 30,000 acre-feet annually,” and that “with roughly 20,000 acre-feet used last year, about 10,000 acre-feet remains available for data centers, river flows, and other uses.” The November slide redraws the March bar the same way: “Current Recycled Water System: 30,000” and “Future Use: ≈ 27,500.” In February and March, Burton had described the network’s capacity as 35,000 acre-feet; the packets do not explain the change. The pending recycled requests alone, about 3,000 acre-feet, would take close to a third of that 10,000 (derived), and the 10,000 is shared with river flows.

Capacity is also uneven. “The recycled water system generally has capacity on the west leg but limited capacity in parts of the east leg,” Marisa Palmer, SAWS’s director of plans and major projects, told the board, and availability for new customers “must be evaluated site by site.” At the April meeting, as the minutes record it, Mayor Gina Ortiz Jones said SAWS “may need to revisit recycled water infrastructure sooner rather than later, particularly if current capacity may only serve two hyperscale users.”

Who pays for the next pipe

The March briefing’s cost recovery slide makes the pricing problem specific. For 2026, SAWS budgeted $6,790,659 to provide recycled water service and $6,487,599 in recycled water revenue. The slide’s title: “Recycled Water Revenue to Cover 95% Cost of Service in 2026.” The gap is $303,060, or 4.7%. For 2027 the board was asked to raise recycled rates up to 10%, which staff estimated at $640,000 of new revenue and said would cover 92% of recycled water service costs, including a new master plan.

That plan is the first large cost. On July 7 the board awarded Garver a contract of up to $1,500,000 for a 2026 Recycled Water System Master Plan, with a condition assessment, capacity expansion needs and “a capital improvement plan … for a 30-year planning period,” per the July packet. The vote was not unanimous: Chairwoman Jamison and trustee Mann voted against. The hydraulic model it will update was last revised in 2022. Burton told the Express-News that SAWS also wants a new line between the Leon Creek and Clouse treatment plants to connect the east and west legs, and more pumps.

The board saw the pressure in January. In the draft minutes of the January 13 meeting, Mayor Jones asked staff to justify investments “particularly for large load customers like data centers, so the budget accurately reflects the main drivers of costs.”

The November slides split the next steps between the utility and the city. For SAWS’s board: “Limitations on water intensive cooling technologies,” and designating data centers “Significant Industrial Users,” with “potential pre-treatment of wastewater.” For the City Council: address the code requirement for “Substitute Water,” the backup supply SAWS must plan for if recycled service fails; implement the recycled water impact fee in the 2028 update; a “Fee by Agreement” bridge; and an expedited cost of service study in 2027. A second slide proposes changing the Utility Service Regulations, because the state certificate “requires provision of potable retail water service, non-potable uses not included.”

The council’s process began with water in its brief. Councilmember Ric Galvan’s Council Consideration Request of October 29, 2025, asked staff for “the water consumption and planning requirements associated with” data centers and for partnerships with “municipal utilities” to “better understand and track data center resource needs,” and the staff memo for the Governance Committee on December 11, 2025, said Development Services “will coordinate with San Antonio Water System (SAWS) and City Public Service (CPS Energy).” Four stakeholder sessions followed. The ordinance the council took up on October 29, 2026, dealt with siting. The staff draft, item 5 on the agenda, set setbacks and kept data centers off the Edwards Aquifer Recharge Zone, and staff had recommended allowing them by right where those standards were met. The draft says nothing about recycled water. The recycled water decisions sit with the SAWS board and the fee items it sends to the council.

Why SAWS does not want to push them out

Burton also said the opposite pressure out loud. If data centers locate outside San Antonio, in places like Medina County with no recycled system, they draw on the Edwards Aquifer, SAWS’s largest drinking water source. “There are impacts that we have by disincentivizing them coming into San Antonio and being on the recycled water system,” he told the Express-News. “It’s a balance.”

The American Water Works Association’s new report, Cooling the Cloud: Considerations for Water Utilities Evaluating Data Center Development, written with Carollo Engineers, frames the same work as four steps: evaluate each project’s cooling technology and its average and peak demands, determine whether the community can accommodate the demand, understand the financial impacts and contracts while “protecting existing customers from financial impacts”, and engage the community early. SAWS’s two briefings touch the first three: cooling technology, supply and cost recovery.

Other states are starting at the first step. New Jersey’s Assembly passed A3966, which asks the Department of Environmental Protection to study data center water use over three and seven years, including “impacts on public water systems, ratepayers, or infrastructure upgrades required to meet demand,” ROI-NJ reported on November 6. It still needs the Senate. SAWS’s own legislative briefing on November 3 lists Texas initiatives for the 2027 session, including public water usage reporting and “Don’t shift infrastructure costs onto consumers.”

Accounts / Cedar Hollow Water Authority / Large-load waterACME · workspace
Large-load water requests
Cedar Hollow Water Authority · recycled water system · as of 6 Nov 2026
Requests on file (acre-feet a year)
RequestAF/yrSource
Request 1 · data center campus1,200Board briefing · 14 Apr 2026, p. 9
Request 2 · data center expansion900Staff memo · 2 Jun 2026, p. 3
Request 3 · data center, use unknown600Board briefing · 14 Apr 2026, p. 9
Total requested2,700
Against what is left
Available to new customers9,000 AF/yrRequested2,700 AF/yr (30%)BasisGeneral manager, board meeting Board minutes · 3 Nov 2026, item 11
Next documents
Rule change Service regulations: reuse service optional, to the board in December
Fee Connection fee by agreement, then city council
The table from a board briefing, kept as a record: each request with the page it came from, set against what the utility says it can still deliver. Drawn for this essay as a sketch. Mockup on invented data: not a customer, not a real utility.

If you sell to utilities

  1. Ask the utility how it counts large-load requests, and whether it has briefed its board on them. SAWS’s March and November packets carry a table of requests by acre-foot; many utilities will have the same list in a staff memo before it reaches a rate case.
  2. A recycled water system with data center demand needs pipe, pumps, storage and controls. In San Antonio, the Leon Creek to Clouse connector between the east and west legs and the Garver master plan’s 30-year capital plan are the projects to follow.
  3. Watch the service rules and the fee items. A change to the Utility Service Regulations and the cooling technology limits go to the SAWS board; the fee by agreement and the impact fee go to City Council.

What I don’t know yet

  • What the board said on November 3. The draft minutes will be in the December packet.
  • The text of the Utility Service Regulations change and of the fee by agreement.
  • Why the system’s capacity went from 35,000 acre-feet in Burton’s February and March remarks to 30,000 in September and November.
  • The adopted text of the council’s October 29 ordinance and the vote record, which are not yet posted.
  • Which data centers the requests belong to. The briefings do not name them.

All of this is as of November 10, 2026.

At AquaIntel we read board packets like the ones SAWS publishes before each meeting, because a staff briefing with a table of requests usually reaches the board months before a fee, a rule change or a capital project does.

Sources


Part of Last Week in US Water Utilities, November 15, 2026, from AquaIntel Research Notes.

If you sell into utilities and want records like these for the accounts in your territory, talk to us→

Share this post:

Related Articles

20 of 121 contract terms

Milwaukee's sewerage district has had a private operator for its two treatment plants since the late 1990s. An audit of the current one, presented on November 9, found it met its permits almost all the time and could prove it met only 20 of its 121 contract obligations. The next contract is already awarded, and in federal court.

2 bond votes and 508 connections

Voters inside the Midland County Utility District have now turned down two water bonds in 18 months. The district already runs a plant and bills customers. Its own engineering report shows how far that is from the system it was created to build.

The three million the board left out

Central Alabama Water's board chose 3.4% for 2027 over the 6.4% its consultants recommended. The difference was $3 million for advanced meters, decided at the same meeting where the utility said close to half its water earns no revenue.