2 bond votes and 508 connections

Cover: Two Bond Votes and 508 Connections  74 3% voted against the Midland County Utility District's $299 million bond on 3 Nov 2026

On election night, November 3, Midland County’s results page showed Proposition A for the Midland County Utility District failing 3,547 to 1,226. That is 74.3% against, on 4,773 votes, in the county’s unofficial final count. The proposition would have authorized up to $299,015,000 in bonds to bring water lines to unincorporated areas south and east of Midland.

It was the district’s second failed bond. In May 2025, voters turned down $645.8 million for the whole system, with about 76% against, according to The Permian Press. The Greenwood Ranger’s headline after this one: “General manager says water expansion could now take decades.” Norman Ashton, who runs the district, told YourBasin the program will now likely take 20 to 30 years, and that without the bond money the district does not qualify for certain grants it would otherwise have been eligible for. He put the result down to cost-of-living worries: “People are hurting for food; they’re hurting for gas and groceries.”

The district already has a working system. It turned on its first water on April 30, 2026, from its own wells and a reverse osmosis plant, and it bills about 508 connections, mostly the Greenwood school district and the new county jail. The question after November 3 is how a district that exists, has a plant and sets rates grows from 508 connections toward the 46,880 its plan calls for.

TEXAS · MIDLAND COUNTY UTILITY DISTRICT · WATERJun 2011Legislature creates the districtH.B. 3111, five-member boardSTATEMay 2013Voters confirm the districtMay 2025$645.8M bond failsabout 76% againstVOTEJun 2025Groundbreaking on wells and plantbuilt with district and county money30 Apr 2026First water from the plantreverse osmosis, 0.5 MGD16 Jul 2026First rates; $299M election called3 Nov 2026$299M bond fails3,547 against, 1,226 forVOTE17 Nov 2026Canvass on the board agendacertified count not yet postedNov 2026Federal WIFIA letter of interestplanned regardless of the voteFEDERAL
Fifteen years from the statute to the first water customers. The two bond votes sit on either side of the plant opening.Special District Local Laws Code Ch. 9016; Midland County Utility District history and news pages; The Permian Press, 30 May 2025, 30 Jul 2026 and 16 Sep 2026; Midland County Elections, 3 Nov 2026.

A district fifteen years in the making

The Texas Legislature created the district in 2011, in Chapter 9016 of the Special District Local Laws Code, as a special district with a five-member board. Voters confirmed it in 2013. I wrote last week about the 1,527 municipal utility districts in Texas, most of which a developer creates and the developer’s bonds pay for. This district went the other way. The area was already built and lived in, and the district has to win a public vote to borrow.

The need is plain in the local reporting. Greenwood is unincorporated, so neither the county nor the City of Midland supplies its water. Homes rely on private wells, a private utility, or water hauled in. Some Greenwood wells have failed, and south of Midland a chromium plume has made some private wells unusable, per The Permian Press. The district covers about 84.5 square miles and about 35,000 residents.

Who votes and who pays are two different groups. Only registered voters who live in the district vote on its bonds, while property owners inside it pay its tax whether or not they are connected. A consultant put the district’s registered voters at about 12,500 in August, which would make turnout on the proposition about 38% (derived). Countywide turnout on November 3 was 46.1%.

ForAgainst
May 2025, $645.8M
24%
76%
Nov 2026, $299M
25.7%
74.3%
Values
TierMay 2025, $645.8MNov 2026, $299M
For24%25.7%
Against76%74.3%
The two bond elections inside the Midland County Utility District, as shares of the vote, in percent. In May 2025 voters turned down $645.8 million for the whole system. On 3 Nov 2026 they turned down $299 million for the first phases, 3,547 to 1,226. The May 2025 split is the reported 76% against, rounded.Midland County Elections, unofficial final election night results, MCUD Proposition A, 3 Nov 2026 (official canvass set for 17 Nov); The Permian Press, 28 Jul 2026 (May 2025).

What the $299 million would have bought

The board approved an engineering report on July 16 and called the election the same day. The Permian Press summarized the report in August. The bond covered three phases:

  1. Greenwood, $91.2 million and about 1,675 connections. That includes $20.1 million to triple the plant from 0.5 to 1.5 million gallons a day, and $35 million set aside to buy or build nearby water and sewer systems.
  2. The chromium plume area south of Midland, $39.8 million and about 2,116 connections.
  3. The areas in between, $148.4 million and about 4,902 connections, including $47.7 million to double the plant again to 3 million gallons a day.

Financing costs added $19.7 million. After that come 19 more projects worth $890.6 million in today’s dollars, among them two new treatment plants and a potable reuse expansion. The whole program is about $1.19 billion (derived), which matches the $1.2 billion figure the general manager, Norman Ashton, has used.

The $299M bond: three phases and financing19 later projects
Capital program, $M
299
890.6
Values
TierCapital program, $M
The $299M bond: three phases and financing299
19 later projects890.6
The district’s capital program as its August 2026 engineering report lays it out, in millions of dollars. The $299 million bond covered the first three phases ($91.2 million, $39.8 million and $148.4 million) and $19.7 million of financing costs, about a quarter of the roughly $1.19 billion total (derived). The other 19 projects, $890.6 million in today’s dollars, include two new treatment plants and potable reuse.Midland County Utility District engineering report, approved 16 Jul 2026, as summarized by The Permian Press, 12 Aug 2026.

So the bond was about a quarter of the program, and it would have reached roughly 8,700 connections of the 46,880 at full buildout. The plan was always to use the bond for the areas with the greatest need, start billing, and then pay for later phases with revenue bonds, federal WIFIA loans (which can cover up to 49% of eligible costs) and state loans and grants. The district said in September that it would send a WIFIA letter of interest in November whatever the result.

ServedPlanned
  • Today: 508 connections
  • Bond phases: 8,693 connections
  • Buildout: 46,880 connections
Water connections in the district: about 508 served today, planned under the three bond phases, and at full buildout. The bond phases would have reached about 8,693 (derived from the three phase counts; the report summary also says roughly 9,200). Full buildout is 46,880.The Permian Press, 12 Aug 2026 (engineering report) and 22 Aug 2026 (current service), Midland County Utility District project list.

What a customer pays

The district adopted its first rates on July 16, designed to mirror the City of Midland’s rates for customers outside city limits: a $34.89 monthly base that includes the first 2,000 gallons, then $9.87 per 1,000 gallons up to 10,000, and a $2,000 connection fee that can be financed at $125 a month for 16 months, per The Permian Press. Ashton estimated the combined bond tax and water bill at about $131 a month for the average home.

Adopted, Jul 2026Proposed, May 2026
  • Adopted, Jul 2026: 2000: $34.89; 4000: 54.63 $; 5000: $64.50; 7000: 84.24 $; 10000: $113.85
  • Proposed, May 2026: 5000: about $43; 10000: $75.90
A monthly residential water bill under the district’s first rates, by gallons used, in dollars: $34.89 covers the first 2,000 gallons and each 1,000 after that is $9.87 up to 10,000 (derived from the adopted schedule). The lighter line is the May 2026 proposal, at the two points reported. The district also charges a $2,000 connection fee.Midland County Utility District rates adopted 16 Jul 2026, as reported by The Permian Press, 30 Jul 2026; May 2026 proposal, The Permian Press, 8 May 2026.

On my arithmetic, a household using 5,000 gallons pays $64.50 a month under the adopted schedule (derived). That is higher than the $50 to $60 Ashton had estimated for 5,000 to 7,000 gallons, and well above the May proposal, which would have charged about $43 at 5,000 gallons. The bond would have added a property tax on top of that. The district’s voter information document, which Texas requires for a bond election, shows the district had no debt and no debt service tax when the election was ordered. It estimated interest of $391.4 million at 5%, and a maximum tax increase of $545.01 a year on a $100,000 homestead, on what it calls conservative assumptions. YourBasin reported that the average homeowner would have paid about $68 a month more.

What I would watch

For anyone who sells to small and growing Texas systems, Midland County is worth following through the winter, because the next steps will each leave a record.

  • The official canvass. It was on the district board’s November 17 agenda, but no certified count had been posted by November 19.
  • The WIFIA letter of interest, which would show how much of the program the district thinks it can finance without general obligation bonds.
  • A pending application to the Texas Water Development Board for about $21 million for a water line, which the board approved in June. Its outcome was not public when I checked. The Texas Water Development Board’s 2027 drinking water intended use plan lists the district for $2.5 million of planning and design money.
  • Park Water, the private utility that holds the service rights for parts of Greenwood. The district and Park Water settled their court fights in July, and the district has said it may buy the system. Phase 1 of the bond set aside $35 million to buy or build systems like it, so any purchase now needs other money.

As of November 19, the district had posted nothing about its next steps after the vote, and its board documents sit on a site that needs a sign-in. Almost everything above comes from the district’s own website and one local newsroom, The Permian Press, which has covered every board meeting. The plant is running, and most of the people it was built for are not yet connected to it.

Sources


Part of Last Week in US Water Utilities, week of November 15, 2026, from AquaIntel Research Notes.

If you sell into utilities and want records like these for the accounts in your territory, talk to us→

Share this post:

Related Articles

20 of 121 contract terms

Milwaukee's sewerage district has had a private operator for its two treatment plants since the late 1990s. An audit of the current one, presented on November 9, found it met its permits almost all the time and could prove it met only 20 of its 121 contract obligations. The next contract is already awarded, and in federal court.

The three million the board left out

Central Alabama Water's board chose 3.4% for 2027 over the 6.4% its consultants recommended. The difference was $3 million for advanced meters, decided at the same meeting where the utility said close to half its water earns no revenue.

Two federal rules, one rate ordinance

Greater Cincinnati Water Works wants 9.5% a year for five years. The City Manager's transmittal names what it pays for, and EPA's own samples from the Bolton plant show why one of those items has a date on it.